Hard1 markMultiple Choice
PMP · Question 67 · Task 3: Assess and manage risks
A project manager is using a 'Risk Burndown Chart'. What is this tool tracking?
A project manager is using a 'Risk Burndown Chart'. What is this tool tracking?
Answer options:
A.
The number of risks identified.
B.
The cumulative severity (probability * impact) of open risks over time.
C.
The money spent on risk responses.
D.
The number of issues.
How to approach this question
Burndown = Remaining. Risk Burndown = Remaining Risk Exposure.
Full Answer
B.The cumulative severity (probability * impact) of open risks over time.✓ Correct
B
Task 3 (Risk). A Risk Burndown chart visualizes the effectiveness of risk management efforts. The line should go down as risks are mitigated or expire.
Common mistakes
Thinking it just counts the number of risks (a low severity risk is not equal to a high severity one).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert