A project manager is leading a project to build a new factory. The local community is concerned about pollution. The PM holds a town hall meeting to listen to their concerns. Which domain is this primarily mapping to?

Answer options:

A.

Process

B.

People

C.

Business Environment

D.

Agile

How to approach this question

Mapping question. Stakeholder interaction = People Domain.

Full Answer

B.People✓ Correct
B
Domain 1: People. Task 9 (Collaborate with stakeholders). While it touches on environment, the activity is engagement.