PMP · Question 66 · Task 10: Manage project changes
A project manager is leading a project to launch a new website. The marketing team wants to change the color scheme one week before launch. This is a cosmetic change but requires significant rework. What should the PM do?
A project manager is leading a project to launch a new website. The marketing team wants to change the color scheme one week before launch. This is a cosmetic change but requires significant rework. What should the PM do?
Answer options:
A.
Do it to keep the client happy.
B.
Reject it immediately.
C.
Assess the impact on the launch date and cost, then present the trade-offs to the marketing team (e.g., 'We can do it, but launch will be delayed by 3 days').
D.
Ask the developers to work overtime.
How to approach this question
Late Change -> Impact Analysis -> Stakeholder Decision.
Full Answer
C.Assess the impact on the launch date and cost, then present the trade-offs to the marketing team (e.g., 'We can do it, but launch will be delayed by 3 days').✓ Correct
C
Task 10 (Changes). The PM's job is to make the consequences of change visible so the business can make an informed decision.
Common mistakes
Saying Yes (Pleaser) or No (Blocker) without data.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert