    PracticePMI PMP®PMI PMP Practice ExamQuestion 65
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeProcessAgileScope

    PMP · Question 65 · Task 8: Plan and manage scope

    A project manager is reviewing the project backlog. The Product Owner has prioritized the items based on 'Business Value'. The Development Team argues that some low-value items should be done first because they are architectural prerequisites. What should the PM do?

    Answer options:

    A.

    Side with the PO; value comes first.

    B.

    Side with the Team; architecture comes first.

    C.

    Facilitate a discussion to help the PO understand the technical dependencies so they can re-order the backlog to account for both value and feasibility.

    D.

    Do the architectural work as a 'hidden' task.

    How to approach this question

    Conflict: Value vs Dependency. Solution: Educate PO on Dependency.

    Full Answer

    C.Facilitate a discussion to help the PO understand the technical dependencies so they can re-order the backlog to account for both value and feasibility.✓ Correct
    C
    Task 8 (Scope) and Task 9 (Collaborate). Backlog ordering is a negotiation between Value and Risk/Dependency. The PM ensures the PO has the technical info to make the right call.

    Common mistakes

    Thinking the PO has absolute power to ignore physics/logic.
    Question 64All questionsQuestion 66

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →