PMP · Question 65 · Task 8: Plan and manage scope
A project manager is reviewing the project backlog. The Product Owner has prioritized the items based on 'Business Value'. The Development Team argues that some low-value items should be done first because they are architectural prerequisites. What should the PM do?
Answer options:
Side with the PO; value comes first.
Side with the Team; architecture comes first.
Facilitate a discussion to help the PO understand the technical dependencies so they can re-order the backlog to account for both value and feasibility.
Do the architectural work as a 'hidden' task.