Hard1 markMultiple Choice
Task 4: Support organizational changeBusiness EnvironmentCulture

PMP · Question 64 · Task 4: Support organizational change

A project manager is leading a project to merge two companies' IT systems. The culture of Company A is formal and hierarchical, while Company B is casual and agile. The teams are clashing. What should the PM do?

Answer options:

A.

Impose Company A's culture on everyone since they acquired Company B.

B.

Facilitate a workshop to acknowledge the differences and co-create a new 'Project Culture' with agreed norms.

C.

Keep the teams separate.

D.

Ignore the culture; focus on the technical tasks.

How to approach this question

Culture Clash -> Hybrid/New Culture.

Full Answer

B.Facilitate a workshop to acknowledge the differences and co-create a new 'Project Culture' with agreed norms.✓ Correct
B
Task 4 (Org Change) and Task 6 (Build a team). Mergers require active cultural management. The PM must build a shared identity.

Common mistakes

Forcing one culture over another.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam