Medium1 markMultiple Choice

PMP · Question 63 · Task 7: Plan and manage quality

A project manager is planning the quality management plan. The project involves mass production of a widget. Testing every single widget is too expensive. Which technique should the PM use?

Answer options:

A.

Benchmarking

B.

Design of Experiments

C.

Statistical Sampling

D.

Checksheets

How to approach this question

Too many to test? -> Sample.

Full Answer

C.Statistical Sampling✓ Correct
C
Task 7 (Quality). Statistical sampling is the standard method for QC when 100% inspection is prohibitive.

Common mistakes

Confusing sampling with benchmarking.