Medium1 markMultiple Choice
PMP · Question 63 · Task 7: Plan and manage quality
A project manager is planning the quality management plan. The project involves mass production of a widget. Testing every single widget is too expensive. Which technique should the PM use?
A project manager is planning the quality management plan. The project involves mass production of a widget. Testing every single widget is too expensive. Which technique should the PM use?
Answer options:
A.
Benchmarking
B.
Design of Experiments
C.
Statistical Sampling
D.
Checksheets
How to approach this question
Too many to test? -> Sample.
Full Answer
C.Statistical Sampling✓ Correct
C
Task 7 (Quality). Statistical sampling is the standard method for QC when 100% inspection is prohibitive.
Common mistakes
Confusing sampling with benchmarking.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert