PMP · Question 63 · Task 7: Plan and manage quality
A project manager is planning the quality management plan. The project involves mass production of a widget. Testing every single widget is too expensive. Which technique should the PM use?
Answer options:
Benchmarking
Design of Experiments
Statistical Sampling
Checksheets