Hard1 markMultiple Choice
PMP · Question 11 · Task 3: Assess and manage risks
A project has a 30% chance of a delay costing $20,000 and a 20% chance of a scope reduction saving $10,000. What is the Expected Monetary Value (EMV) of these uncertainties?
A project has a 30% chance of a delay costing $20,000 and a 20% chance of a scope reduction saving $10,000. What is the Expected Monetary Value (EMV) of these uncertainties?
Answer options:
A.
-$6,000
B.
-$4,000
C.
$4,000
D.
-$8,000
How to approach this question
Calculate EMV for each risk separately (Threat = negative, Opportunity = positive) and sum them.
Full Answer
B.-$4,000✓ Correct
EMV is the sum of probability-weighted impacts. Threat: 0.3 * -20k = -6k. Opportunity: 0.2 * +10k = +2k. Sum = -4k.
Common mistakes
Forgetting that costs are negative values.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert