Hard1 markMultiple Choice

PMP · Question 46 · Task 3: Assess and manage risks

A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?

Answer options:

A.

Use the backup supplier immediately and accept the cost overrun.

B.

Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.

C.

Look for a third supplier.

D.

Cancel the project.

How to approach this question

Risk happened -> Cost increased -> Change Control for Money.

Full Answer

B.Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.✓ Correct
B
Task 3 (Risk) and Task 5 (Budget). Executing a risk response that costs more than expected requires budget management (Change Request).

Common mistakes

Spending money you don't have (A) without approval.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam