Hard1 markMultiple Choice
PMP · Question 46 · Task 3: Assess and manage risks
A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?
A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?
Answer options:
A.
Use the backup supplier immediately and accept the cost overrun.
B.
Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.
C.
Look for a third supplier.
D.
Cancel the project.
How to approach this question
Risk happened -> Cost increased -> Change Control for Money.
Full Answer
B.Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.✓ Correct
B
Task 3 (Risk) and Task 5 (Budget). Executing a risk response that costs more than expected requires budget management (Change Request).
Common mistakes
Spending money you don't have (A) without approval.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert