For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 47
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleProcessAgile

    PMP · Question 47 · Task 6: Plan and manage schedule

    A project manager is leading an agile team. The team is complaining that the daily standup is taking 30 minutes instead of 15. What is the MOST likely cause?

    Answer options:

    A.

    The team is too large.

    B.

    The Scrum Master is not present.

    C.

    The team is solving problems during the meeting instead of just reporting status/blockers.

    D.

    There are too many stakeholders observing.

    How to approach this question

    Diagnosis: Why is the standup long? People are talking too much. About what? Solutions.

    Full Answer

    C.The team is solving problems during the meeting instead of just reporting status/blockers.✓ Correct
    C
    Task 2 (Lead). Efficient meetings require discipline. The PM/Scrum Master must coach the team to take problem-solving to a 'parking lot' or '16th minute'.

    Common mistakes

    Thinking the team size is the issue (unless it's huge, e.g., >15).
    Question 46All questionsQuestion 48

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →