PMP · Question 47 · Task 6: Plan and manage schedule
A project manager is leading an agile team. The team is complaining that the daily standup is taking 30 minutes instead of 15. What is the MOST likely cause?
Answer options:
The team is too large.
The Scrum Master is not present.
The team is solving problems during the meeting instead of just reporting status/blockers.
There are too many stakeholders observing.