Hard1 markMultiple Choice
PMP · Question 47 · Task 6: Plan and manage schedule
A project manager is leading an agile team. The team is complaining that the daily standup is taking 30 minutes instead of 15. What is the MOST likely cause?
A project manager is leading an agile team. The team is complaining that the daily standup is taking 30 minutes instead of 15. What is the MOST likely cause?
Answer options:
A.
The team is too large.
B.
The Scrum Master is not present.
C.
The team is solving problems during the meeting instead of just reporting status/blockers.
D.
There are too many stakeholders observing.
How to approach this question
Diagnosis: Why is the standup long? People are talking too much. About what? Solutions.
Full Answer
C.The team is solving problems during the meeting instead of just reporting status/blockers.✓ Correct
Task 2 (Lead). Efficient meetings require discipline. The PM/Scrum Master must coach the team to take problem-solving to a 'parking lot' or '16th minute'.
Common mistakes
Thinking the team size is the issue (unless it's huge, e.g., >15).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert