For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 48
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeProcessScopePlanning

    PMP · Question 48 · Task 8: Plan and manage scope

    A project manager is creating a WBS. The team is struggling to decompose a specific complex deliverable that will be built six months from now. What should the PM do?

    Answer options:

    A.

    Force the team to estimate it now to complete the baseline.

    B.

    Use Rolling Wave Planning to decompose the near-term work now and leave the future work at a high level.

    C.

    Remove the deliverable from the project.

    D.

    Assign it to a vendor.

    How to approach this question

    Future + Uncertain = Rolling Wave.

    Full Answer

    B.Use Rolling Wave Planning to decompose the near-term work now and leave the future work at a high level.✓ Correct
    B
    Task 8 (Scope). Rolling Wave Planning is the practice of planning near-term work in detail and future work at a higher level (Planning Packages), elaborating as the time approaches.

    Common mistakes

    Thinking you must have a 100% detailed WBS at the start (impossible for large projects).
    Question 47All questionsQuestion 49

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →