PMP · Question 48 · Task 8: Plan and manage scope
A project manager is creating a WBS. The team is struggling to decompose a specific complex deliverable that will be built six months from now. What should the PM do?
Answer options:
Force the team to estimate it now to complete the baseline.
Use Rolling Wave Planning to decompose the near-term work now and leave the future work at a high level.
Remove the deliverable from the project.
Assign it to a vendor.