PMP · Question 49 · Task 16: Ensure knowledge transfer
A project manager is leading a project to develop a new AI tool. The technology is new to the organization. The PM wants to ensure that knowledge is shared among the team members effectively. Which technique is BEST?
A project manager is leading a project to develop a new AI tool. The technology is new to the organization. The PM wants to ensure that knowledge is shared among the team members effectively. Which technique is BEST?
Answer options:
A.
Send everyone to individual external training courses.
B.
Create a detailed wiki and mandate everyone read it.
C.
Implement Pair Programming or Mob Programming sessions.
D.
Hire a consultant to do the work.
How to approach this question
Knowledge Transfer (Task 16). Active > Passive.
Full Answer
C.Implement Pair Programming or Mob Programming sessions.✓ Correct
C
Task 16 (Knowledge Transfer) and Task 6 (Build a team). Pairing/Mobbing spreads knowledge instantly and reduces 'key person' risk.
Common mistakes
Relying on documentation (B) for complex tacit knowledge transfer.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert