Hard1 markMultiple Choice
Task 16: Ensure knowledge transferProcessKnowledge TransferAgile

PMP · Question 49 · Task 16: Ensure knowledge transfer

A project manager is leading a project to develop a new AI tool. The technology is new to the organization. The PM wants to ensure that knowledge is shared among the team members effectively. Which technique is BEST?

Answer options:

A.

Send everyone to individual external training courses.

B.

Create a detailed wiki and mandate everyone read it.

C.

Implement Pair Programming or Mob Programming sessions.

D.

Hire a consultant to do the work.

How to approach this question

Knowledge Transfer (Task 16). Active > Passive.

Full Answer

C.Implement Pair Programming or Mob Programming sessions.✓ Correct
C
Task 16 (Knowledge Transfer) and Task 6 (Build a team). Pairing/Mobbing spreads knowledge instantly and reduces 'key person' risk.

Common mistakes

Relying on documentation (B) for complex tacit knowledge transfer.