Hard1 markMultiple Choice
PMP · Question 50 · Task 17: Plan and manage project closure
A project manager is closing a project that was terminated early due to budget cuts. What should the PM do with the partially completed deliverables?
A project manager is closing a project that was terminated early due to budget cuts. What should the PM do with the partially completed deliverables?
Answer options:
A.
Discard them as they are unfinished.
B.
Document their status and transfer them to the operations team or sponsor.
C.
Finish them using personal time.
D.
Give them to the team members as a portfolio.
How to approach this question
Closure (Task 17). Terminated projects still need formal closure.
Full Answer
B.Document their status and transfer them to the operations team or sponsor.✓ Correct
B
Task 17 (Closure). When a project is cancelled, the PM must document the status of all work and transfer it to the appropriate owner to salvage any value.
Common mistakes
Thinking cancelled means 'stop and leave'.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert