For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 50
    Hard1 markMultiple Choice
    Task 17: Plan and manage project closureProcessClosure

    PMP · Question 50 · Task 17: Plan and manage project closure

    A project manager is closing a project that was terminated early due to budget cuts. What should the PM do with the partially completed deliverables?

    Answer options:

    A.

    Discard them as they are unfinished.

    B.

    Document their status and transfer them to the operations team or sponsor.

    C.

    Finish them using personal time.

    D.

    Give them to the team members as a portfolio.

    How to approach this question

    Closure (Task 17). Terminated projects still need formal closure.

    Full Answer

    B.Document their status and transfer them to the operations team or sponsor.✓ Correct
    Task 17 (Closure). When a project is cancelled, the PM must document the status of all work and transfer it to the appropriate owner to salvage any value.

    Common mistakes

    Thinking cancelled means 'stop and leave'.
    Question 49All questionsQuestion 51

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →