Hard1 markMultiple Choice
Task 2: Lead a teamPeopleLeadership

PMP · Question 51 · Task 2: Lead a team

A project manager is leading a project to update a company's HR policy. The project has high stakeholder resistance. The PM decides to use a 'Consultative' decision-making style. What does this mean?

Answer options:

A.

The PM makes the decision alone and announces it.

B.

The team votes and the majority wins.

C.

The PM gathers input from all stakeholders but retains the final decision-making authority.

D.

The PM delegates the decision to the team completely.

How to approach this question

Match Style to Definition. Consultative = 'I listen, then I decide'.

Full Answer

C.The PM gathers input from all stakeholders but retains the final decision-making authority.✓ Correct
C
Task 2 (Lead a team). Different styles suit different situations. Consultative is useful when you need expertise/buy-in but accountability rests with the leader.

Common mistakes

Confusing Consultative with Democratic (Voting).