Hard1 markMultiple Choice
PMP · Question 51 · Task 2: Lead a team
A project manager is leading a project to update a company's HR policy. The project has high stakeholder resistance. The PM decides to use a 'Consultative' decision-making style. What does this mean?
A project manager is leading a project to update a company's HR policy. The project has high stakeholder resistance. The PM decides to use a 'Consultative' decision-making style. What does this mean?
Answer options:
A.
The PM makes the decision alone and announces it.
B.
The team votes and the majority wins.
C.
The PM gathers input from all stakeholders but retains the final decision-making authority.
D.
The PM delegates the decision to the team completely.
How to approach this question
Match Style to Definition. Consultative = 'I listen, then I decide'.
Full Answer
C.The PM gathers input from all stakeholders but retains the final decision-making authority.✓ Correct
C
Task 2 (Lead a team). Different styles suit different situations. Consultative is useful when you need expertise/buy-in but accountability rests with the leader.
Common mistakes
Confusing Consultative with Democratic (Voting).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert