Medium1 markMultiple Choice
PMP · Question 91 · Task 3: Assess and manage risks
A project manager is leading a project to develop a new AI algorithm. The project is high risk. The PM decides to use an 'Agile Spike'. What is this?
A project manager is leading a project to develop a new AI algorithm. The project is high risk. The PM decides to use an 'Agile Spike'. What is this?
Answer options:
A.
A sudden increase in work.
B.
A time-boxed research or experiment activity to reduce uncertainty/risk.
C.
A team celebration.
D.
A type of bug.
How to approach this question
Term -> Definition. Spike = Research.
Full Answer
B.A time-boxed research or experiment activity to reduce uncertainty/risk.✓ Correct
Task 3 (Risk) and Task 13 (Methodology). Spikes are used in Agile to explore technical risks or requirements before committing to the full work.
Common mistakes
Thinking Spikes are for doing the actual work (they are for learning how to do the work).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert