Medium1 markMultiple Choice

PMP · Question 91 · Task 3: Assess and manage risks

A project manager is leading a project to develop a new AI algorithm. The project is high risk. The PM decides to use an 'Agile Spike'. What is this?

Answer options:

A.

A sudden increase in work.

B.

A time-boxed research or experiment activity to reduce uncertainty/risk.

C.

A team celebration.

D.

A type of bug.

How to approach this question

Term -> Definition. Spike = Research.

Full Answer

B.A time-boxed research or experiment activity to reduce uncertainty/risk.✓ Correct
Task 3 (Risk) and Task 13 (Methodology). Spikes are used in Agile to explore technical risks or requirements before committing to the full work.

Common mistakes

Thinking Spikes are for doing the actual work (they are for learning how to do the work).

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam