PMP · Question 91 · Task 3: Assess and manage risks
A project manager is leading a project to develop a new AI algorithm. The project is high risk. The PM decides to use an 'Agile Spike'. What is this?
Answer options:
A sudden increase in work.
A time-boxed research or experiment activity to reduce uncertainty/risk.
A team celebration.
A type of bug.