PMP · Question 90 · Task 12: Define team ground rules
A project manager is leading a project with a team of experts. The PM notices that the experts are very opinionated and often talk over each other in meetings. The PM decides to use a 'talking stick' rule. What is the PM doing?
A project manager is leading a project with a team of experts. The PM notices that the experts are very opinionated and often talk over each other in meetings. The PM decides to use a 'talking stick' rule. What is the PM doing?
Answer options:
A.
Treating them like children.
B.
Establishing ground rules to manage communication and ensure respect.
C.
Using a democratic leadership style.
D.
Suppressing free speech.
How to approach this question
Technique -> Purpose. Talking Stick = Ground Rule/Facilitation.
Full Answer
B.Establishing ground rules to manage communication and ensure respect.✓ Correct
Task 12 (Ground Rules). The PM helps the team define rules of engagement to make meetings productive.
Common mistakes
Dismissing simple techniques as 'childish'.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert