A project manager is leading a project to implement a new payroll system. The project is nearing completion. The PM wants to ensure that the benefits of the project are realized. Who is primarily responsible for realizing the benefits AFTER the project is closed?
A project manager is leading a project to implement a new payroll system. The project is nearing completion. The PM wants to ensure that the benefits of the project are realized. Who is primarily responsible for realizing the benefits AFTER the project is closed?
Answer options:
A.
The Project Manager
B.
The Project Team
C.
The Business Owner / Operations Management
D.
The Vendor
How to approach this question
Project = Output. Operations = Outcome/Benefit.
Full Answer
C.The Business Owner / Operations Management✓ Correct
C
Task 2 (Benefits). The PM ensures benefits *can* be realized, but the Business Owner is responsible for *actually* realizing them after handover.
Common mistakes
Thinking the PM is responsible for long-term ROI.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert