Hard1 markMultiple Choice

PMP · Question 92 · Task 2: Evaluate and deliver project benefits

A project manager is leading a project to implement a new payroll system. The project is nearing completion. The PM wants to ensure that the benefits of the project are realized. Who is primarily responsible for realizing the benefits AFTER the project is closed?

Answer options:

A.

The Project Manager

B.

The Project Team

C.

The Business Owner / Operations Management

D.

The Vendor

How to approach this question

Project = Output. Operations = Outcome/Benefit.

Full Answer

C.The Business Owner / Operations Management✓ Correct
C
Task 2 (Benefits). The PM ensures benefits *can* be realized, but the Business Owner is responsible for *actually* realizing them after handover.

Common mistakes

Thinking the PM is responsible for long-term ROI.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam