PMP · Question 93 · Task 6: Build a team

A project manager is leading a project with a team that has never worked together. They are polite but guarded. Which stage of the Tuckman ladder are they in?

Answer options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

How to approach this question

Tuckman Stages. Polite = Forming. Fighting = Storming. Habits = Norming. Flow = Performing.

Full Answer

A.Forming✓ Correct
A
Task 6 (Build a team). Recognizing the stage helps the PM choose the right leadership style (Directive for Forming).

Common mistakes

Confusing Forming (Polite) with Norming (Cooperative).