Medium1 markMultiple Choice
PMP · Question 93 · Task 6: Build a team
A project manager is leading a project with a team that has never worked together. They are polite but guarded. Which stage of the Tuckman ladder are they in?
A project manager is leading a project with a team that has never worked together. They are polite but guarded. Which stage of the Tuckman ladder are they in?
Answer options:
A.
Forming
B.
Storming
C.
Norming
D.
Performing
How to approach this question
Tuckman Stages. Polite = Forming. Fighting = Storming. Habits = Norming. Flow = Performing.
Full Answer
A.Forming✓ Correct
A
Task 6 (Build a team). Recognizing the stage helps the PM choose the right leadership style (Directive for Forming).
Common mistakes
Confusing Forming (Polite) with Norming (Cooperative).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert