Medium1 markMultiple Choice

PMP · Question 94 · Task 7: Plan and manage quality

A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the concrete quality meets the standards. Which document defines the quality standards?

Answer options:

A.

Quality Audit

B.

Quality Management Plan

C.

Risk Register

D.

Issue Log

How to approach this question

Standards = Plan.

Full Answer

B.Quality Management Plan✓ Correct
B
Task 7 (Quality). The Quality Management Plan identifies the standards (e.g., ASTM concrete specs) and the activities to verify them.

Common mistakes

Confusing the Plan (Rules) with the Audit (Check).