Medium1 markMultiple Choice
PMP · Question 94 · Task 7: Plan and manage quality
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the concrete quality meets the standards. Which document defines the quality standards?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the concrete quality meets the standards. Which document defines the quality standards?
Answer options:
A.
Quality Audit
B.
Quality Management Plan
C.
Risk Register
D.
Issue Log
How to approach this question
Standards = Plan.
Full Answer
B.Quality Management Plan✓ Correct
B
Task 7 (Quality). The Quality Management Plan identifies the standards (e.g., ASTM concrete specs) and the activities to verify them.
Common mistakes
Confusing the Plan (Rules) with the Audit (Check).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert