PMP · Question 94 · Task 7: Plan and manage quality
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the concrete quality meets the standards. Which document defines the quality standards?
Answer options:
Quality Audit
Quality Management Plan
Risk Register
Issue Log