Medium1 markMultiple Choice
PMP · Question 95 · Task 12: Manage project artifacts
A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to track the remaining work in the sprint. Which chart should the PM use?
A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to track the remaining work in the sprint. Which chart should the PM use?
Answer options:
A.
Sprint Burndown Chart
B.
Gantt Chart
C.
Control Chart
D.
Pareto Chart
How to approach this question
Remaining Work + Sprint = Burndown.
Full Answer
A.Sprint Burndown Chart✓ Correct
A
Task 6 (Schedule) and Task 12 (Artifacts). The Sprint Burndown is the primary tactical tracking tool for the team.
Common mistakes
Confusing Burndown with Burnup (Total work done).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert