    PracticePMI PMP®PMI PMP Practice ExamQuestion 95
    Medium1 markMultiple Choice
    Task 12: Manage project artifactsProcessAgileTools

    PMP · Question 95 · Task 12: Manage project artifacts

    A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to track the remaining work in the sprint. Which chart should the PM use?

    Answer options:

    A.

    Sprint Burndown Chart

    B.

    Gantt Chart

    C.

    Control Chart

    D.

    Pareto Chart

    How to approach this question

    Remaining Work + Sprint = Burndown.

    Full Answer

    A.Sprint Burndown Chart✓ Correct
    Task 6 (Schedule) and Task 12 (Artifacts). The Sprint Burndown is the primary tactical tracking tool for the team.

    Common mistakes

    Confusing Burndown with Burnup (Total work done).
    Question 94All questionsQuestion 96

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →