Medium1 markMultiple Choice

PMP · Question 95 · Task 12: Manage project artifacts

A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to track the remaining work in the sprint. Which chart should the PM use?

Answer options:

A.

Sprint Burndown Chart

B.

Gantt Chart

C.

Control Chart

D.

Pareto Chart

How to approach this question

Remaining Work + Sprint = Burndown.

Full Answer

A.Sprint Burndown Chart✓ Correct
A
Task 6 (Schedule) and Task 12 (Artifacts). The Sprint Burndown is the primary tactical tracking tool for the team.

Common mistakes

Confusing Burndown with Burnup (Total work done).