    PracticePMI PMP®PMI PMP Practice ExamQuestion 10
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentCompliance

    PMP · Question 10 · Task 1: Plan and manage project compliance

    A project manager discovers that a team member has been using a free online tool to convert sensitive client data, violating the company's data security policy. The team member was unaware of the policy. What should the project manager do FIRST?

    Answer options:

    A.

    Fire the team member immediately for the security breach.

    B.

    Instruct the team member to stop using the tool and assess the extent of the data exposure.

    C.

    Update the risk register and schedule training for the team next week.

    D.

    Report the breach to the client immediately.

    How to approach this question

    Compliance breaches require immediate 'Stop and Assess' logic.

    Full Answer

    B.Instruct the team member to stop using the tool and assess the extent of the data exposure.✓ Correct
    When compliance is violated, the first step is to stop the non-compliant activity and assess the damage. Reporting and training follow.

    Common mistakes

    Jumping to punishment (A) or external reporting (D) before understanding the scope of the issue.
    Question 09All questionsQuestion 11

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →