PMP · Question 11 · Task 4: Engage stakeholders
In a predictive project, the project manager is preparing the final report. The project was completed on time and under budget, but the client is unhappy because the product does not integrate well with their legacy systems. This requirement was never mentioned in the scope statement. Which action should the project manager have taken earlier to prevent this?
Answer options:
Included a buffer in the budget for undefined requirements.
Conducted more frequent quality control inspections.
Identified and engaged key stakeholders to validate assumptions and constraints during planning.
Used an agile methodology instead of predictive.
114 questions · hints · full answers · grading