A project manager is leading a large transformation project. A new government regulation is announced that will impact the project's compliance requirements in six months. What should the project manager do FIRST?
A project manager is leading a large transformation project. A new government regulation is announced that will impact the project's compliance requirements in six months. What should the project manager do FIRST?
Answer options:
A.
Immediately implement changes to the project scope to comply with the new regulation.
B.
Analyze the impact of the new regulation on the project's scope, schedule, and cost.
C.
Submit a change request to the Change Control Board (CCB).
D.
Inform the sponsor that the project will be delayed.
How to approach this question
Follow the sequence: Event -> Analyze Impact -> Create Change Request -> Approval -> Implement.
Full Answer
B.Analyze the impact of the new regulation on the project's scope, schedule, and cost.✓ Correct
B
Changes in the business environment (Task 3) require an impact analysis before any action is taken.
Common mistakes
Skipping the analysis step and jumping to solutions or change requests.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert