    PracticePMI PMP®PMI PMP Practice ExamQuestion 13
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeProcessScopeAgile

    PMP · Question 13 · Task 8: Plan and manage scope

    During a sprint review, the client requests a new feature that is very different from the current product goal. The team is excited about the idea, but the Product Owner is concerned about the remaining budget. What is the BEST course of action?

    Answer options:

    A.

    Reject the request as it is outside the current product goal.

    B.

    Add the feature to the next sprint backlog immediately to satisfy the client.

    C.

    Add the item to the product backlog and prioritize it against existing items to see if it fits within the budget/value proposition.

    D.

    Ask the client to sign a new contract for the additional feature.

    How to approach this question

    Agile handles change via the Backlog. New idea -> Backlog -> Prioritize.

    Full Answer

    C.Add the item to the product backlog and prioritize it against existing items to see if it fits within the budget/value proposition.✓ Correct
    The Product Backlog is the holding tank for all potential work. The PO manages priority and value there. If the new feature is high value, it might displace lower value items, keeping the budget neutral.

    Common mistakes

    Thinking 'Agile' means saying yes to everything immediately (B) or that contracts prevent change (D).
    Question 12All questionsQuestion 14

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →