Hard1 markMultiple Choice

PMP · Question 16 · Task 6: Plan and manage schedule

A project manager is planning a project with a high degree of uncertainty regarding the final product design. The stakeholders are highly involved and want to see progress frequently. Which scheduling method is MOST appropriate?

Answer options:

A.

Critical Path Method (CPM)

B.

Iterative scheduling with a backlog

C.

Gantt Chart with hard milestones

D.

Monte Carlo Simulation

How to approach this question

Match the project characteristics (Uncertainty, High Involvement) to the methodology.

Full Answer

B.Iterative scheduling with a backlog✓ Correct
B
Agile/Iterative scheduling allows for adaptive planning as the design emerges, satisfying the stakeholder need for progress visibility.

Common mistakes

Applying predictive tools (CPM, Gantt) to adaptive problems.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam