Hard1 markMultiple Choice
PMP · Question 16 · Task 6: Plan and manage schedule
A project manager is planning a project with a high degree of uncertainty regarding the final product design. The stakeholders are highly involved and want to see progress frequently. Which scheduling method is MOST appropriate?
A project manager is planning a project with a high degree of uncertainty regarding the final product design. The stakeholders are highly involved and want to see progress frequently. Which scheduling method is MOST appropriate?
Answer options:
A.
Critical Path Method (CPM)
B.
Iterative scheduling with a backlog
C.
Gantt Chart with hard milestones
D.
Monte Carlo Simulation
How to approach this question
Match the project characteristics (Uncertainty, High Involvement) to the methodology.
Full Answer
B.Iterative scheduling with a backlog✓ Correct
B
Agile/Iterative scheduling allows for adaptive planning as the design emerges, satisfying the stakeholder need for progress visibility.
Common mistakes
Applying predictive tools (CPM, Gantt) to adaptive problems.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard