PMP · Question 17 · Task 14: Promote team performance through EI
A key team member requests a week of leave during a critical phase of the project. This will delay a major milestone. The team member is burnt out and insists on the break. What should the project manager do?
Answer options:
Deny the leave request citing project criticality.
Approve the leave and accept the delay without informing stakeholders.
Approve the leave for the well-being of the staff, and work with the team to re-plan or compress the schedule (crashing/fast-tracking) to mitigate the impact.
Ask the team member to work remotely during their leave.