For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 17
    Hard1 markMultiple Choice
    Task 14: Promote team performance through EIPeopleEmotional IntelligenceSchedule

    PMP · Question 17 · Task 14: Promote team performance through EI

    A key team member requests a week of leave during a critical phase of the project. This will delay a major milestone. The team member is burnt out and insists on the break. What should the project manager do?

    Answer options:

    A.

    Deny the leave request citing project criticality.

    B.

    Approve the leave and accept the delay without informing stakeholders.

    C.

    Approve the leave for the well-being of the staff, and work with the team to re-plan or compress the schedule (crashing/fast-tracking) to mitigate the impact.

    D.

    Ask the team member to work remotely during their leave.

    How to approach this question

    Balance Empathy (People) with Performance (Process).

    Full Answer

    C.Approve the leave for the well-being of the staff, and work with the team to re-plan or compress the schedule (crashing/fast-tracking) to mitigate the impact.✓ Correct
    Emotional Intelligence (Task 14) requires recognizing burnout. The PM must support the person AND manage the project impact through schedule compression techniques.

    Common mistakes

    Prioritizing the schedule over health (A) or failing to manage the consequence (B).
    Question 16All questionsQuestion 18

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →