PMP · Question 22 · Task 6: Plan and manage schedule
An agile team is consistently failing to meet their sprint commitment. They commit to 40 story points but only deliver 25. This has happened for three sprints. What should the project manager (acting as Scrum Master) do?
Answer options:
Add more resources to the team to help them reach 40 points.
Facilitate a retrospective to identify the root cause of the over-commitment and encourage the team to use yesterday's weather (historical velocity) for planning.
Dictate that the team only commit to 25 points in the next sprint.
Extend the sprint duration to allow them to finish the work.
114 questions · hints · full answers · grading