Hard1 markMultiple Choice
PMP · Question 22 · Task 6: Plan and manage schedule
An agile team is consistently failing to meet their sprint commitment. They commit to 40 story points but only deliver 25. This has happened for three sprints. What should the project manager (acting as Scrum Master) do?
An agile team is consistently failing to meet their sprint commitment. They commit to 40 story points but only deliver 25. This has happened for three sprints. What should the project manager (acting as Scrum Master) do?
Answer options:
A.
Add more resources to the team to help them reach 40 points.
B.
Facilitate a retrospective to identify the root cause of the over-commitment and encourage the team to use yesterday's weather (historical velocity) for planning.
C.
Dictate that the team only commit to 25 points in the next sprint.
D.
Extend the sprint duration to allow them to finish the work.
How to approach this question
The problem is 'Over-commitment'. The solution is 'Empirical Planning' (Velocity).
Full Answer
B.Facilitate a retrospective to identify the root cause of the over-commitment and encourage the team to use yesterday's weather (historical velocity) for planning.✓ Correct
B
Agile relies on empirical data. If velocity is 25, planning for 40 is a fantasy. The PM helps the team accept their actual capacity.
Common mistakes
Changing the rules (extending sprint) or forcing the number (dictating).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert