For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 22
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleProcessScheduleAgile

    PMP · Question 22 · Task 6: Plan and manage schedule

    An agile team is consistently failing to meet their sprint commitment. They commit to 40 story points but only deliver 25. This has happened for three sprints. What should the project manager (acting as Scrum Master) do?

    Answer options:

    A.

    Add more resources to the team to help them reach 40 points.

    B.

    Facilitate a retrospective to identify the root cause of the over-commitment and encourage the team to use yesterday's weather (historical velocity) for planning.

    C.

    Dictate that the team only commit to 25 points in the next sprint.

    D.

    Extend the sprint duration to allow them to finish the work.

    How to approach this question

    The problem is 'Over-commitment'. The solution is 'Empirical Planning' (Velocity).

    Full Answer

    B.Facilitate a retrospective to identify the root cause of the over-commitment and encourage the team to use yesterday's weather (historical velocity) for planning.✓ Correct
    Agile relies on empirical data. If velocity is 25, planning for 40 is a fantasy. The PM helps the team accept their actual capacity.

    Common mistakes

    Changing the rules (extending sprint) or forcing the number (dictating).
    Question 21All questionsQuestion 23

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →