    Hard1 markMultiple Choice
    Task 4: Engage stakeholdersProcessStakeholders

    PMP · Question 23 · Task 4: Engage stakeholders

    A project manager is identifying stakeholders for a new construction project. They know that a local environmental group will likely oppose the project. How should this group be categorized and managed?

    Answer options:

    A.

    Low Power, High Interest -> Monitor

    B.

    High Power, Low Interest -> Keep Satisfied

    C.

    High Power, High Interest -> Manage Closely

    D.

    Ignore them as they are negative stakeholders.

    How to approach this question

    Assess Power (Influence) and Interest (Concern). Activists usually have both.

    Full Answer

    C.High Power, High Interest -> Manage Closely✓ Correct
    C
    Stakeholder Analysis (Task 4). Negative stakeholders are still stakeholders and often require the MOST attention to prevent them from derailing the project.

    Common mistakes

    Underestimating the power of external groups.
    Question 22All questionsQuestion 24

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →