    PracticePMI PMP®PMI PMP Practice ExamQuestion 24
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrganizational Change

    PMP · Question 24 · Task 4: Support organizational change

    During a project to implement a new CRM system, the sales team (end users) refuses to attend training sessions, claiming they are too busy. The project manager is concerned about adoption. What is the BEST strategy?

    Answer options:

    A.

    Report the sales team to the VP of Sales for non-compliance.

    B.

    Meet with the sales team leads to understand their constraints and explain the value/benefits of the new system to them (WIIFM).

    C.

    Cancel the training and send them the user manuals.

    D.

    Proceed with the rollout; they will learn it when they have to use it.

    How to approach this question

    Resistance to change is solved by 'What's In It For Me' (WIIFM) and empathy, not force.

    Full Answer

    B.Meet with the sales team leads to understand their constraints and explain the value/benefits of the new system to them (WIIFM).✓ Correct
    Task 4 (Org Change) and Task 5 (Training). Resistance is natural. The PM must use influence and explain the value proposition to get buy-in.

    Common mistakes

    Using authority (A) instead of influence.
    Question 23All questionsQuestion 25

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →