PMP · Question 21 · Task 10: Manage project changes
A stakeholder requests a change to the project scope. The project manager checks the change management plan and sees that the project is in the execution phase. What is the FIRST step the project manager should take?
A stakeholder requests a change to the project scope. The project manager checks the change management plan and sees that the project is in the execution phase. What is the FIRST step the project manager should take?
Answer options:
A.
Deny the request because the scope is baselined.
B.
Implement the change if it adds value.
C.
Evaluate the impact of the change on all project constraints (cost, schedule, risk, quality).
D.
Ask the sponsor for approval.
How to approach this question
Change Request Flow: Request -> Assess Impact -> CCB -> Decision.
Full Answer
C.Evaluate the impact of the change on all project constraints (cost, schedule, risk, quality).✓ Correct
C
Task 10 (Manage Changes) requires a structured approach. Impact analysis provides the data needed for the Change Control Board to make a decision.
Common mistakes
Skipping the assessment step.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert