    PracticePMI PMP®PMI PMP Practice ExamQuestion 20
    Hard1 markMultiple Choice
    Task 2: Lead a teamPeopleTeam BuildingLeadership

    PMP · Question 20 · Task 2: Lead a team

    A project manager observes that the team is struggling to reach consensus on technical decisions, leading to long meetings and delays. The team is in the 'Storming' phase. Which leadership style is MOST appropriate?

    Answer options:

    A.

    Delegating - Let the team figure it out to build self-reliance.

    B.

    Coaching/Facilitating - Guide the team through the conflict resolution process.

    C.

    Directing - Make the decisions for them to save time.

    D.

    Supporting - Step back and only intervene if asked.

    How to approach this question

    Match Leadership Style (Situational Leadership) to Team Phase. Storming -> Coaching.

    Full Answer

    B.Coaching/Facilitating - Guide the team through the conflict resolution process.✓ Correct
    B
    Tuckman's Ladder: Storming is characterized by conflict. The leader must facilitate resolution and establish norms (Coaching) to help them reach Norming.

    Common mistakes

    Thinking 'Agile' always means Delegating. You only delegate to a Performing team.
    Question 19All questionsQuestion 21

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →