Hard1 markMultiple Choice
PMP · Question 19 · Task 17: Plan and manage project closure
A project manager is closing a project. The deliverables have been accepted, and the final report is written. Which TWO activities must still be completed to officially close the project?
A project manager is closing a project. The deliverables have been accepted, and the final report is written. Which TWO activities must still be completed to officially close the project?
Answer options:
A.
Release project resources
B.
Validate scope
C.
Calculate the final CPI
D.
Archive project documents and update the lessons learned repository
E.
Conduct the kick-off meeting
F.
Perform qualitative risk analysis
How to approach this question
Select TWO. Think: What happens at the very end? Releasing people and saving data.
Full Answer
A,D
Project Closure (Task 17) involves administrative closure (archiving, lessons learned) and resource release.
Common mistakes
Confusing 'Validate Scope' (Client Acceptance) with Closure. Acceptance is an input to closure.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert