Hard1 markMultiple Choice

PMP · Question 19 · Task 17: Plan and manage project closure

A project manager is closing a project. The deliverables have been accepted, and the final report is written. Which TWO activities must still be completed to officially close the project?

Answer options:

A.

Release project resources

B.

Validate scope

C.

Calculate the final CPI

D.

Archive project documents and update the lessons learned repository

E.

Conduct the kick-off meeting

F.

Perform qualitative risk analysis

How to approach this question

Select TWO. Think: What happens at the very end? Releasing people and saving data.

Full Answer

A,D
Project Closure (Task 17) involves administrative closure (archiving, lessons learned) and resource release.

Common mistakes

Confusing 'Validate Scope' (Client Acceptance) with Closure. Acceptance is an input to closure.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam