PMP · Question 55 · Task 6: Plan and manage schedule
A project manager is leading a project with a team that is new to Agile. The team is struggling to estimate stories using Story Points. They keep trying to equate points to hours. What should the PM do?
Answer options:
Let them use hours since it's easier for them.
Create a conversion table: 1 point = 4 hours.
Facilitate an exercise using 'Affinity Estimation' (grouping items by size) to help them understand relative sizing without numbers first.
Estimate the points for them.
114 questions · hints · full answers · grading