For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 55
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleProcessAgileEstimation

    PMP · Question 55 · Task 6: Plan and manage schedule

    A project manager is leading a project with a team that is new to Agile. The team is struggling to estimate stories using Story Points. They keep trying to equate points to hours. What should the PM do?

    Answer options:

    A.

    Let them use hours since it's easier for them.

    B.

    Create a conversion table: 1 point = 4 hours.

    C.

    Facilitate an exercise using 'Affinity Estimation' (grouping items by size) to help them understand relative sizing without numbers first.

    D.

    Estimate the points for them.

    How to approach this question

    Coaching (Task 13/5). Move from Absolute to Relative estimation.

    Full Answer

    C.Facilitate an exercise using 'Affinity Estimation' (grouping items by size) to help them understand relative sizing without numbers first.✓ Correct
    C
    Task 6 (Schedule) and Task 13 (Methodology). Relative estimation is a key agile concept. The PM coaches the team to compare items (T-shirt sizing/Affinity) rather than predict time.

    Common mistakes

    Mapping points to hours (B).
    Question 54All questionsQuestion 56

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →