    PracticePMI PMP®PMI PMP Practice ExamQuestion 54
    Medium1 markMultiple Choice
    Task 7: Plan and manage qualityProcessQualityTools

    PMP · Question 54 · Task 7: Plan and manage quality

    A project manager is using a Fishbone (Ishikawa) diagram with the team. What is the primary purpose of this activity?

    Answer options:

    A.

    To schedule tasks.

    B.

    To identify the root cause of a quality problem or risk.

    C.

    To prioritize requirements.

    D.

    To calculate the critical path.

    How to approach this question

    Tool -> Purpose. Fishbone = Root Cause.

    Full Answer

    B.To identify the root cause of a quality problem or risk.✓ Correct
    Task 7 (Quality) and Task 1 (Conflict/Issues). Root cause analysis is essential for solving problems permanently.

    Common mistakes

    Confusing diagram types.
    Question 53All questionsQuestion 55

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →