PMP · Question 54 · Task 7: Plan and manage quality
A project manager is using a Fishbone (Ishikawa) diagram with the team. What is the primary purpose of this activity?
Answer options:
To schedule tasks.
To identify the root cause of a quality problem or risk.
To prioritize requirements.
To calculate the critical path.