Medium1 markMultiple Choice

PMP · Question 54 · Task 7: Plan and manage quality

A project manager is using a Fishbone (Ishikawa) diagram with the team. What is the primary purpose of this activity?

Answer options:

A.

To schedule tasks.

B.

To identify the root cause of a quality problem or risk.

C.

To prioritize requirements.

D.

To calculate the critical path.

How to approach this question

Tool -> Purpose. Fishbone = Root Cause.

Full Answer

B.To identify the root cause of a quality problem or risk.✓ Correct
B
Task 7 (Quality) and Task 1 (Conflict/Issues). Root cause analysis is essential for solving problems permanently.

Common mistakes

Confusing diagram types.