Medium1 markMultiple Choice
PMP · Question 54 · Task 7: Plan and manage quality
A project manager is using a Fishbone (Ishikawa) diagram with the team. What is the primary purpose of this activity?
A project manager is using a Fishbone (Ishikawa) diagram with the team. What is the primary purpose of this activity?
Answer options:
A.
To schedule tasks.
B.
To identify the root cause of a quality problem or risk.
C.
To prioritize requirements.
D.
To calculate the critical path.
How to approach this question
Tool -> Purpose. Fishbone = Root Cause.
Full Answer
B.To identify the root cause of a quality problem or risk.✓ Correct
B
Task 7 (Quality) and Task 1 (Conflict/Issues). Root cause analysis is essential for solving problems permanently.
Common mistakes
Confusing diagram types.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert