Hard1 markMultiple Choice
PMP · Question 53 · Task 17: Plan and manage project transitions
A project manager is leading a project to deploy a new software system. The system is ready, but the operations team refuses to accept it because they haven't been trained. The project deadline is today. What should the PM do?
A project manager is leading a project to deploy a new software system. The system is ready, but the operations team refuses to accept it because they haven't been trained. The project deadline is today. What should the PM do?
Answer options:
A.
Force the handover and close the project.
B.
Extend the project indefinitely.
C.
Delay the closure, keep the project team engaged to support operations, and execute a crash training plan.
D.
Blame the operations manager.
How to approach this question
Transition requires Receiver Readiness. If not ready, PM must support.
Full Answer
C.Delay the closure, keep the project team engaged to support operations, and execute a crash training plan.✓ Correct
C
Task 17 (Transitions). Successful transition requires knowledge transfer and training. If missed, the project is not done.
Common mistakes
Thinking 'Product done' = 'Project done'.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert