For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 56
    Hard1 markMultiple Choice
    Task 11: Plan and manage procurementProcessProcurement

    PMP · Question 56 · Task 11: Plan and manage procurement

    A project manager is reviewing the procurement strategy. The project requires a vendor to develop a proprietary algorithm. The IP (Intellectual Property) rights are a critical concern. Which document must clearly define the IP ownership?

    Answer options:

    A.

    Non-Disclosure Agreement (NDA)

    B.

    The Contract / Agreement (specifically the Terms and Conditions)

    C.

    Statement of Work (SOW)

    D.

    Risk Register

    How to approach this question

    Legal ownership = Contract.

    Full Answer

    B.The Contract / Agreement (specifically the Terms and Conditions)✓ Correct
    B
    Task 11 (Procurement). IP rights are a critical part of project agreements (Task 8). They must be explicit in the contract.

    Common mistakes

    Thinking NDA covers ownership.
    Question 55All questionsQuestion 57

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →