PMP · Question 56 · Task 11: Plan and manage procurement
A project manager is reviewing the procurement strategy. The project requires a vendor to develop a proprietary algorithm. The IP (Intellectual Property) rights are a critical concern. Which document must clearly define the IP ownership?
Answer options:
Non-Disclosure Agreement (NDA)
The Contract / Agreement (specifically the Terms and Conditions)
Statement of Work (SOW)
Risk Register