Medium1 markMultiple Choice

PMP · Question 57 · Task 7: Plan and manage quality

A project manager is leading a project to reduce waste in a manufacturing process. The team suggests using 'Kaizen' events. What is the goal of a Kaizen event?

Answer options:

A.

Continuous, incremental improvement.

B.

Radical process re-engineering.

C.

Statistical process control.

D.

Just-in-Time delivery.

How to approach this question

Term -> Definition. Kaizen = Continuous Improvement.

Full Answer

A.Continuous, incremental improvement.✓ Correct
A
Task 7 (Quality). Kaizen is a core quality/agile concept focusing on continuous improvement.

Common mistakes

Confusing it with radical change.