Medium1 markMultiple Choice
PMP · Question 57 · Task 7: Plan and manage quality
A project manager is leading a project to reduce waste in a manufacturing process. The team suggests using 'Kaizen' events. What is the goal of a Kaizen event?
A project manager is leading a project to reduce waste in a manufacturing process. The team suggests using 'Kaizen' events. What is the goal of a Kaizen event?
Answer options:
A.
Continuous, incremental improvement.
B.
Radical process re-engineering.
C.
Statistical process control.
D.
Just-in-Time delivery.
How to approach this question
Term -> Definition. Kaizen = Continuous Improvement.
Full Answer
A.Continuous, incremental improvement.✓ Correct
A
Task 7 (Quality). Kaizen is a core quality/agile concept focusing on continuous improvement.
Common mistakes
Confusing it with radical change.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert