Hard1 markMultiple Choice

PMP · Question 58 · Task 12: Define team ground rules

A project manager is leading a team that is geographically dispersed. The PM wants to ensure that the team feels united and shares a common purpose. Which document is BEST suited to help with this?

Answer options:

A.

WBS

B.

Team Charter / Social Contract

C.

Resource Calendar

D.

RACI Matrix

How to approach this question

Culture/Values = Team Charter.

Full Answer

B.Team Charter / Social Contract✓ Correct
B
Task 2 (Lead) and Task 12 (Ground Rules). The Team Charter is the foundation of team culture.

Common mistakes

Thinking the Project Charter (Business document) is the Team Charter (Social document).

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam