PMP · Question 59 · Task 5: Plan and manage budget
A project manager is monitoring a project and sees that the SPI is 0.8 and the CPI is 1.2. What does this mean?
Answer options:
Ahead of schedule, Over budget.
Behind schedule, Over budget.
Behind schedule, Under budget.
Ahead of schedule, Under budget.