Medium1 markMultiple Choice
Task 5: Plan and manage budgetProcessEVMData Analysis

PMP · Question 59 · Task 5: Plan and manage budget

A project manager is monitoring a project and sees that the SPI is 0.8 and the CPI is 1.2. What does this mean?

Answer options:

A.

Ahead of schedule, Over budget.

B.

Behind schedule, Over budget.

C.

Behind schedule, Under budget.

D.

Ahead of schedule, Under budget.

How to approach this question

EVM Basics: >1 is Good. <1 is Bad. SPI=Schedule, CPI=Cost.

Full Answer

C.Behind schedule, Under budget.✓ Correct
C
Task 5 (Budget) and Task 6 (Schedule). Interpreting EVM metrics is a required skill. SPI < 1 means work is delayed. CPI > 1 means work is costing less than planned.

Common mistakes

Mixing up SPI and CPI or the <1/>1 rule.