Medium1 markMultiple Choice
PMP · Question 59 · Task 5: Plan and manage budget
A project manager is monitoring a project and sees that the SPI is 0.8 and the CPI is 1.2. What does this mean?
A project manager is monitoring a project and sees that the SPI is 0.8 and the CPI is 1.2. What does this mean?
Answer options:
A.
Ahead of schedule, Over budget.
B.
Behind schedule, Over budget.
C.
Behind schedule, Under budget.
D.
Ahead of schedule, Under budget.
How to approach this question
EVM Basics: >1 is Good. <1 is Bad. SPI=Schedule, CPI=Cost.
Full Answer
C.Behind schedule, Under budget.✓ Correct
C
Task 5 (Budget) and Task 6 (Schedule). Interpreting EVM metrics is a required skill. SPI < 1 means work is delayed. CPI > 1 means work is costing less than planned.
Common mistakes
Mixing up SPI and CPI or the <1/>1 rule.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert