A project manager is leading a project to build a bridge. The project uses a predictive lifecycle. During excavation, the team finds archaeological artifacts. Work must stop. What is the PM's FIRST action?

Answer options:

A.

Update the schedule.

B.

Secure the site and notify the appropriate authorities/stakeholders as per the compliance plan.

C.

Move the bridge location.

D.

Ignore it and keep digging.

How to approach this question

Compliance Event -> Stop -> Notify.

Full Answer

B.Secure the site and notify the appropriate authorities/stakeholders as per the compliance plan.✓ Correct
B
Task 1 (Compliance). Regulatory/Legal issues require immediate adherence to the compliance plan.