PMP · Question 20 · Task 6: Plan and manage schedule
A project is using a hybrid approach. The hardware components follow a predictive schedule, while software is agile. The hardware delivery is delayed by 2 weeks due to supply chain issues. This hardware is required for the software team's integration testing in the current sprint. What should the PM do?
A project is using a hybrid approach. The hardware components follow a predictive schedule, while software is agile. The hardware delivery is delayed by 2 weeks due to supply chain issues. This hardware is required for the software team's integration testing in the current sprint. What should the PM do?
Answer options:
A.
Pause the software sprint until the hardware arrives.
B.
Force the hardware vendor to expedite delivery.
C.
Work with the Product Owner to reprioritize the backlog, moving integration stories to a future sprint and pulling in other work.
D.
Extend the sprint duration by 2 weeks.
How to approach this question
Leverage the flexibility of the Agile side of the hybrid project to accommodate the rigid constraint of the Predictive side.
Full Answer
C.Work with the Product Owner to reprioritize the backlog, moving integration stories to a future sprint and pulling in other work.✓ Correct
C
In hybrid projects, the agile stream can adapt to delays in the predictive stream by reordering the backlog.
Common mistakes
Breaking the timebox (D) or halting work (A).
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
Expert