PMP · Question 19 · Task 5: Plan and manage budget and resources
A project has a Budget at Completion (BAC) of $200,000. The project is 50% complete. The Actual Cost (AC) is $120,000. The Earned Value (EV) is $100,000. The project manager expects the current cost variance to continue. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols)
20 questions · hints · full answers · grading