PMP · Question 86 · Task 6: Plan and manage schedule
A project manager is leading a project to build a new stadium. The project is using a predictive lifecycle. The steel beams are delayed by 4 weeks due to a strike. This activity is on the critical path. What is the impact on the project finish date?
Answer options:
No impact if there is float.
The project will be delayed by 4 weeks unless corrective action (crashing/fast-tracking) is taken.
The project will be delayed by 2 weeks.
The PM can use the management reserve to fix the time.