Hard1 markMultiple Choice
Task 6: Build a teamPeopleTeam Building

PMP · Question 87 · Task 6: Build a team

A project manager is leading a team that is experiencing high turnover. New members are joining frequently. What should the PM do to maintain performance?

Answer options:

A.

Stop hiring new people.

B.

Assign the new people to simple tasks only.

C.

Implement a robust onboarding process and knowledge transfer mechanisms (e.g., mentoring, documentation).

D.

Ask the remaining team members to work harder.

How to approach this question

Turnover -> Onboarding/Knowledge Transfer.

Full Answer

C.Implement a robust onboarding process and knowledge transfer mechanisms (e.g., mentoring, documentation).✓ Correct
Task 6 (Build a team) and Task 16 (Knowledge Transfer). High turnover requires a system to ramp people up quickly to minimize the 'Storming' phase.

Common mistakes

Ignoring the cost of onboarding.