Hard1 markMultiple Choice
PMP · Question 88 · Task 6: Plan and manage schedule
A project manager is leading a project to develop a new video game. The team is using Agile. The marketing team needs a firm release date for the ad campaign. The team says, 'We will be done when we are done.' What should the PM do?
A project manager is leading a project to develop a new video game. The team is using Agile. The marketing team needs a firm release date for the ad campaign. The team says, 'We will be done when we are done.' What should the PM do?
Answer options:
A.
Force the team to commit to a date.
B.
Tell marketing to wait.
C.
Work with the team to use their velocity and backlog to forecast a release range (e.g., 'Likely between Oct 1 and Oct 15') and communicate this probability to marketing.
D.
Pick a date and hope.
How to approach this question
Agile Forecasting = Velocity + Backlog = Range.
Full Answer
C.Work with the team to use their velocity and backlog to forecast a release range (e.g., 'Likely between Oct 1 and Oct 15') and communicate this probability to marketing.✓ Correct
C
Task 6 (Schedule). Agile doesn't mean 'no dates'. It means 'dates based on data'. The PM uses velocity to project completion.
Common mistakes
Thinking Agile teams can't give dates.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert