Medium1 markShort Answer
Task 6: Plan and manage scheduleProcessScheduleCalculation

PMP · Question 26 · Task 6: Plan and manage schedule

A project has a critical path of A-B-C-D. Task A is 3 days, B is 4 days, C is 5 days, D is 2 days. The project manager decides to 'crash' the project by reducing Task C by 2 days at a cost of $1000. What is the new duration of the critical path? (Enter number only)

How to approach this question

Sum the original path. Subtract the crashed amount.

Full Answer

12
Original Path: 3+4+5+2 = 14 days. Crash C by 2 days -> C becomes 3 days. New Path: 3+4+3+2 = 12 days.

Common mistakes

Calculation errors.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam