    PracticePMI PMP®PMI PMP Practice ExamQuestion 27
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transferProcessLessons Learned

    PMP · Question 27 · Task 16: Ensure knowledge transfer

    A project manager is preparing for a lessons learned session at the end of a phase. Which TWO actions will MOST ensure the session is effective?

    Answer options:

    A.

    Invite only the project sponsor and senior management.

    B.

    Create a safe, blame-free environment where team members can speak openly.

    C.

    Focus on actionable improvements for future phases/projects rather than just listing what went wrong.

    D.

    Focus primarily on identifying who was responsible for the errors.

    E.

    Send a survey instead of holding a meeting to save time.

    F.

    Wait until the very end of the project to capture all lessons at once.

    How to approach this question

    Select TWO. Effective Retrospectives/Lessons Learned need Safety and Actionability.

    Full Answer

    Task 16 (Knowledge Transfer). To get value, you need honesty (Safety) and utility (Actionable improvements).

    Common mistakes

    Focusing on blame (D) or administration (A, E).
    Question 26All questionsQuestion 28

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →