Hard1 markMultiple Choice
PMP · Question 28 · Task 8: Negotiate project agreements
A project manager is negotiating a contract with a vendor. The vendor proposes a clause that allows them to increase rates by 10% annually. The project budget is fixed. What is the BEST negotiation strategy?
A project manager is negotiating a contract with a vendor. The vendor proposes a clause that allows them to increase rates by 10% annually. The project budget is fixed. What is the BEST negotiation strategy?
Answer options:
A.
Accept the clause to get the deal signed quickly.
B.
Propose a performance-based incentive where rate increases are tied to meeting specific KPIs.
C.
Threaten to cancel the negotiation if they don't remove the clause.
D.
Reduce the project scope to afford the rate increase.
How to approach this question
Negotiation (Task 8) should be collaborative. Look for the trade-off.
Full Answer
B.Propose a performance-based incentive where rate increases are tied to meeting specific KPIs.✓ Correct
B
Principled negotiation focuses on interests. The vendor wants more money; the PM wants budget certainty/value. Tying pay to performance satisfies both.
Common mistakes
Capitulating (A) or being aggressive (C).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert