Medium1 markMultiple Choice
Task 6: Plan and manage scheduleProcessEVMData Analysis

PMP · Question 103 · Task 6: Plan and manage schedule

A project manager is leading a project to build a new factory. The project is using a predictive lifecycle. The PM wants to ensure that the project is on schedule. The PM calculates the Schedule Variance (SV). SV = EV - PV. The SV is -$10,000. What does this mean?

Answer options:

A.

The project is ahead of schedule.

B.

The project is behind schedule.

C.

The project is over budget.

D.

The project is under budget.

How to approach this question

SV < 0 = Behind.

Full Answer

B.The project is behind schedule.✓ Correct
Task 6 (Schedule). SV measures schedule performance in currency. Negative means you accomplished less value than planned by that date.

Common mistakes

Thinking SV is about cost because it has a $ sign. It's about 'Value of work done' vs 'Value of work planned'.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam