PMP · Question 102 · Task 13: Determine appropriate project methodology

A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to ensure that the team is constantly improving. Which event is designed for this?

Answer options:

A.

Daily Standup

B.

Sprint Review

C.

Sprint Retrospective

D.

Backlog Refinement

How to approach this question

Improvement = Retrospective.

Full Answer

C.Sprint Retrospective✓ Correct
C
Task 3 (Support team performance) and Task 7 (Quality). The Retrospective is the engine of continuous improvement in Agile.

Common mistakes

Confusing Review (Product) with Retrospective (Process).