Easy1 markMultiple Choice
PMP · Question 102 · Task 13: Determine appropriate project methodology
A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to ensure that the team is constantly improving. Which event is designed for this?
A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to ensure that the team is constantly improving. Which event is designed for this?
Answer options:
A.
Daily Standup
B.
Sprint Review
C.
Sprint Retrospective
D.
Backlog Refinement
How to approach this question
Improvement = Retrospective.
Full Answer
C.Sprint Retrospective✓ Correct
C
Task 3 (Support team performance) and Task 7 (Quality). The Retrospective is the engine of continuous improvement in Agile.
Common mistakes
Confusing Review (Product) with Retrospective (Process).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert