Hard1 markMultiple Choice
PMP · Question 101 · Task 5: Plan and manage budget and resources
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the To Complete Performance Index (TCPI). The TCPI is 1.2. What does this mean?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the To Complete Performance Index (TCPI). The TCPI is 1.2. What does this mean?
Answer options:
A.
The project can continue at the current efficiency.
B.
The project team must perform 20% more efficiently than planned for the remaining work to stay within budget.
C.
The project has extra money.
D.
The project is ahead of schedule.
How to approach this question
TCPI > 1 = Harder. TCPI < 1 = Easier.
Full Answer
B.The project team must perform 20% more efficiently than planned for the remaining work to stay within budget.✓ Correct
B
Task 5 (Budget). TCPI is the 'Work Remaining / Funds Remaining'. If > 1, the work > funds, so you must be hyper-efficient.
Common mistakes
Confusing TCPI with CPI (where > 1 is good). For TCPI, > 1 is 'Hard/Bad'.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert